Demo mode — fictional company, synthetic data and simulated integrations
CoreBI Construction 360 — Operations Command Centre
Calder & Wren Construction Ltd (fictional) · 12 live projects · 120 operatives · data as at Monday 19 October 2026. No real HR, payroll, accounting or email systems are connected.
Owner overview
Calder & Wren Construction Ltd (fictional) · 12 live projects · figures as at 19 Oct 2026. Every figure is labelled as actual, committed, forecast or estimated.
Planned = approved budget × time elapsed. Actual = recorded and approved cost.
Revised contract value − forecast cost at completion. Red marks projects below the 5% threshold.
Approved labour cost by week against the planned run rate (rate card × planned headcount)
Worker-days by trade, w/c 19 Oct, for the selected projects
Projects needing attention
| Project | Name | PM | Status | Progress vs plan | Est. margin | Last week labour vs plan |
|---|---|---|---|---|---|---|
| St Anne's Library Restoration | Natalie Brooks | Delayed | 62% vs 75% | -5.1% | +1% | |
| Kingsway Primary School Extension | Claire Mitchell | Delayed | 65% vs 75% | 0.6% | +2% | |
| Meridian Logistics Warehouse M&E | Kwame Mensah | At risk | 81% vs 85% | 0.9% | +58% | |
| Canal Street Office Refurbishment | Sanjay Patel | At risk | 78% vs 80% | 3.9% | +26% | |
| Greenway Leisure Centre Upgrade | Gareth Owens | At risk | 74% vs 74% | 4.0% | +1% | |
| Foundry Lane Lab Fit-out | Sanjay Patel | At risk | 55% vs 56% | 13.1% | +19% |
Definitions: Actual recorded and approved costs · Committed actual + approved, un-invoiced orders · Forecast actual ÷ % complete · Estimated revised contract − forecast. Total portfolio forecast at completion: £10,609,960.